You are hereHawkeye Green Energy Grid

Hawkeye Green Energy Grid


Take Action
Provincial EA is currently inactive, pending draft Terms of Reference. No public comment period has opened up

Review Status BC EAO: Pre-application CEAA: No application
EPA Status Submitted to Clean Power Call

Hawkeye Energy Corporation is proposing to build 12 runof-
river hydroelectric generation facilities with a combined capacity of 151 MW in the Toba Inlet, Powell River and Jervis Inlet drainage basins. Depending on the selected route to Malaspina Substation, 135-150 km of 230 kV transmission system will be built.

More detail is in Hawkeye Energy's project description, posted September 12, 2008 by the EAO.

Project Info

Hawkeye Energy Corp.

BC EAO Project Info

CEAA Nothing on file

Location map (1.7 MB)